Schedule

The timeline to complete the milestones for the Coastal Texas Study is as follows:

Initial Assessment

Approval to begin feasibility stage of study

November 2015

Alternative Evaluation Analysis

Identify viable projects for consideration, evaluation and comparison

June 2016

Identify projects for feasibility analysis. Draft Tentatively Selected Plan

May 2018

Release draft integrated feasibility report and environmental impact statement (DIFR-EIS) for public input

October 2018

Formal public meetings held by the USACE and the GLO

November – December 2018

Feasibility Analysis

Public Open Houses to provide study updates

February 2020

Further refinement of the Feasibility Report and Environmental Impact Statement based on public feedback, in-depth environmental and engineering analyses and evaluation for USACE endorsement

February 2019 – Summer 2020

Public Open Houses to provide study updates

September 2020

Release revised Feasibility Report and Environmental Impact Statement for second public review and comment period (including formal public meetings)

Fall 2020

Final Feasibility Report released for review by the Texas Governor’s Office, federal, state and local elected officials in the affected areas, state and federal resource agencies, and tribes

July 2021

Chief’s Report submittal to Congress

Summer 2022


timeline